The energy required per unit mass to grind limestone particles of very large size to 100 ?m is 12.7 kWh/ton. An estimate (using Bonds law) of the energy to grind the particles from a very large size to 50 ?m is________________?

A. 6.35 kWh/ton

B. 25.4 kWh/ton

C. 18 kWh/ton

D. 9.0 kWh/ton