Select the incorrect statement?
Found an error? Read our corrections policy and submit a sourced correction below. You can also share a useful explanation in your own words.
A. Latest finish of an activity is the late event time of the node it enters.
B. Latest start of an activity is its latest finish minus its duration.
C. Earliest start of an activity is the early event time of the node it leaves.