Pick up the incorrect statement from the following?

A. each activity consumes a given time

B. an activity of the project is denoted by an arrow on the net work

C. the arrows are drawn (to scale from) left to right

D. the tail of the arrow indicates the start of the activity

E. the head of the arrow indicates the end of,the activity!