Pick up the correct statement from the following?

A. The earthwork calculation in excavation is made from the difference in levels obtained with a level

B. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers

C. In order to check up the average depth of excavation, Dead man s are left at the mid-widths of borrow pits

D. All the above