P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?

A. = 2

B. 7

C. 8

D. t; Q takes 12/2 days = 6 days to complete the work

E. 9

F. t; x = 12