JCB (Which makes agricultural and construction equipment) has the opportunity to purchase a new factory today that will provide them with a Rs50 million return four years from now If prevailing interest rates are 6 percent, what is the maximum that the project can cost for JCB to be willing to undertake the project ?

A. Rs 34,538,902

B. Rs 53,406,002

C. Rs 39,604,682

D. Rs 43,456,838