In time-cost optimization of a project, crashing is done____________?
Found an error? Read our corrections policy and submit a sourced correction below. You can also share a useful explanation in your own words.
B. only on activities lying on the orginal critical path and having flatter cost slopes
C. on all the activities
D. on all the activities lying on the critical path