Free float is mainly used to_________________?

A. establish priorities

B. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

C. identify the activities, which can be delayed without affecting the total float of succeeding activity

D. identify the activities which can be delayed without affecting the total float of preceding activity