Crash project duration is obtained by summing the________________?
Found an error? Read our corrections policy and submit a sourced correction below. You can also share a useful explanation in your own words.
A. normal durations for all the activities
B. crash durations for all activities
D. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities