Who authenticates the schedule of authorised expenditure under Article 83?

A. The Prime Minister

B. The Speaker of the National Assembly

C. The Auditor-General

D. The Finance Minister alone

Explanation

Article 83 requires the Prime Minister to authenticate by signature the schedule showing grants made or deemed made and the sums needed for charged expenditure.

Source

Pakistan Code — Constitution of Pakistan (Twenty-Seventh Amendment incorporated)