Consider the following data for a company during the month of June 2012 Budgeted hours 4,000 Standard hours for actual production 4,400 Maximum possible hours in the budget period 4,800 Actual hours 3,800 The activity ratio of the company during the month is

A. 117%

B. 95%

C. 111%

D. 120%