Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is_________________?

A. 6 months

B. 3 months

C. 12 months

D. 24 months