2 men and 12 women can finish a job in 4 days. 4 men and 6 women can do the same job in 5 days. Find the time taken by 1 man and 1 woman to complete the job.
Found an error? Read our corrections policy and report it in the comments below.
B. 25 days
C. 30 days
D. 20 days
Found an error? Read our corrections policy and report it in the comments below.