1722. Crash project duration is obtained by summing the________________?
comments icon0

A. crash durations for all activities

B. normal durations for all the activities

C. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

D. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

1723. Economic saving of time results by crashing_________________?
comments icon0

A. costliest critical activity

B. cheapest non-critical activity

C. cheapest critical activity

D. costliest non-critical activity

1724. A rigid-jointed plane frame is stable and statically determinate if_______________?
comments icon0

A. (m + r) = 3j

B. (m + 3r) = 3j

C. re m is number of members, r is reaction components and j is number of joints

D. (3m + r) = 3j

E. (m + r) = 2j

1727. Effects of shear force and axial force on plastic moment capacity of a structure are respectively to_________________?
comments icon0

A. decrease and increase

B. increase and increase

C. decrease and decrease

D. increase and decrease

1729. The type of bearing plate used in all joints and on curves to give better bearing area to the rails is___________________?
comments icon0

A. none of the above

B. cast iron anti creep bearing plate

C. mild steel canted bearing plate

D. flat mild steel bearing plate

1731. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
comments icon0

A. expected time of activity A is greater than the expected time of activity B

B. expected time of activity B is greater than the expected time of activity A

C. expected time of both activities A and B are same

D. none of the above

1734. The degree of kinematic indeterminacy of a pin-jointed space frame is_____________?
comments icon0

A. j-2r

B. 3j-r

C. 2j-r

D. j-3r

E. re j is number of joints and r is reaction components

1735. During the construction period, price variation clause in contracts caters to__________________?
comments icon0
A. variation in cost in materials element, labour element and petrol-oil-lubricant element

B. variation in total cost of the project on an ad hoc basis

C. increase in rates of only important materials

D. rate of inflation

1736. In time-cost optimization of a project, crashing is done____________?
comments icon0

A. on all the activities

B. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

C. only on activities lying on the orginal critical path and having flatter cost slopes

D. on all the activities lying on the critical path

1737. Pick up the correct statement for the web stiffeners?
comments icon0

A. for horizontal stiffeners, d is the clear distance between the horizontal stiffener and the tension flange

B. all the above

C. d is the distance between flange angles or the clear distance between flanges

D. vertical stiffeners are spaced at a distance not greater than 1.5 d and not less than 0.33 d

1738. To ensure exact gauge, the gauge tie plates are provided at_________________?
comments icon0

A. toe of the switch

B. nose of crossing

C. both (A) and (B)

D. none of the above

1740. Drifters can be used to drill_________________?
comments icon0

A. horizontal or up holes

B. only down holes

C. only up holes

D. horizoral, down or up holes