The time which results in the least possible direct cost of an activity is known as________________?

A. none of the above

B. standard time

C. normal time

D. slow time

E. crash time

Be the first to comment if anything wrong with this mcq
Your comment successfully submitted!
It will automatically posted after review and approval by our staff member.