The important file in making a PERT is__________________?

A. no activity from any event can be started from preceding event till it is completed

B. length of arrow has nothing to do with time

C. every activity must be completed before end point is reached

D. all of the above

E. an event cant be accomplished until activities leading to it are completed

Found an error? Read our corrections policy and submit a sourced correction below. You can also share a useful explanation in your own words.

Discuss the answer or suggest a sourced correction
Thank you for contributing.
Your comment was submitted and will appear after editorial review.

Your email is used only for moderation and is never displayed. Spam, copied material and fabricated endorsements are rejected.