Pick up the incorrect statement from the following?

A. the arrows are drawn (to scale from) left to right

B. the head of the arrow indicates the end of,the activity!

C. the tail of the arrow indicates the start of the activity

D. an activity of the project is denoted by an arrow on the net work

E. each activity consumes a given time