PERT is___________________?

A. an analytic tool in concept

B. based on three time estimates for activities linking up two events

C. all of the above

D. used for research and development projects

E. limit up of event oriented diagrams

Found an error? Read our corrections policy and submit a sourced correction below. You can also share a useful explanation in your own words.

Discuss the answer or suggest a sourced correction
Thank you for contributing.
Your comment was submitted and will appear after editorial review.

Your email is used only for moderation and is never displayed. Spam, copied material and fabricated endorsements are rejected.