Critical Path Net Work helps an engineer_________________?

A. none of the above

B. all of the above

C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. to divert the resources from non-critical advanced activities to critical activities

E. to concentrate his attention on critical activities