Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

A. latest start time of succeeding event -earliest finish time of preceding event activity time

B. latest finish time of event earliest finish time of the event

C. none of the above

D. anyone of the above

E. latest start time of the event earliest start time of the event