A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand ?

A. 1.6 hours per unit

B. 1.4 hours per unit

C. 1.0 hour per unit

D. 1.2 hours per unit

Found an error? Read our corrections policy and submit a sourced correction below. You can also share a useful explanation in your own words.

Discuss the answer or suggest a sourced correction
Thank you for contributing.
Your comment was submitted and will appear after editorial review.

Your email is used only for moderation and is never displayed. Spam, copied material and fabricated endorsements are rejected.