estimating and costing Mcqs
1. Pick up the excavation where measurements are made in square metres for payment ?
comments icon0

A. Ordinary cuttings up to 1 m

B. Surface dressing up to 15 cm depths

C. Surface excavation up to 30 cm depths

D. Both B. and C.
2. The inspection pit or chamber is a manhole provided in a base drainage system________________?
comments icon0

A. At every change of direction

B. All the above

C. At every change of gradient

D. At every 30 m intervals

5. The main factor to be considered while preparing a detailed estimate, is________________?
comments icon0

A. Availability of materials

B. All the above

C. Quantity of the materials

D. Transportation of materials

6. While preparing a detailed estimate__________________?
comments icon0
A. All the above

B. Dimension should be measured correct to 0.01 m

C. Volume should be measured correct to 0.01 cum

D. Area should be measured correct to 0.01 sqm

8. The measurement is not made in square metres in case of________________?
comments icon0
A. R.C. Chhajja

B. D.P.C. (Damp proof course)

C. Concrete Jeffries

D. Form works

9. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken________________?
comments icon0

A. 1.20 litres for 15 users

B. 1.80 litres for 5 to 10 users

C. All the above

D. 1.35 for 20 users

11. In case of laying gullies, siphons, intercepting traps, the cost includes_______________?
comments icon0

A. Setting and laying

B. Connection to drains

C. All of these

D. Bed concreting

14. According to ISI method of measurement, the order of the sequence is_________________?
comments icon0

A. None of these

B. Height, length, breadth

C. Length, breadth, height

D. Breadth, length, height

15. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________?
comments icon0

A. One fourth breadth of wall on each side

B. Breadth of the wall

C. Half breadth of wall on each side

D. None of these

18. Pick up the correct statement regarding the centre line method of estimating a building?
comments icon0
A. All the above

B. The centre line is worked out separately for different sections of walls of a building

C. The centre line length is reduced by half the layer of main wall joining the partition wall

D. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

19. The most reliable estimate is_________________?
comments icon0

A. Cube rate estimate

B. Preliminary estimate

C. Plinth area estimate

D. Detailed estimate
21. The following item of earth work is not measured separately ?
comments icon0

A. Steps in deep excavation

B. All the above

C. Setting out of works

D. Site clearance

22. The rate of an item of work depends on_________________?
comments icon0
A. All the above

B. Specifications of materials

C. Specifications of works

D. Proportion of mortar

23. The centre line method is specially adopted for estimating_________________?
comments icon0

A. Circular buildings

B. All the above

C. Hexagonal buildings

D. Octagonal buildings

24. The measurement is made for stone work in square metre in case of________________?
comments icon0

A. Building work

B. Columns, lintels, copings

C. A. and D. of the above

D. Wall facing

25. While estimating the qualities for the construction of a building, the correct metric unit is________________?
comments icon0

A. Cubic metre for area

B. Metre for length

C. Square metres for volume

D. Litre for capacity
26. According to Indian Standards Institute, the actual size of modular bricks is_______________?
comments icon0

A. 25 cm 13 cm 7.5 cm

B. 19 cm 9 cm 9 cmD. 20 cm 10 cm 10 cm

C. 23 cm 11.5 cm 7.5 cm

28. While estimating a reinforced cement structure, the omitted cover of concrete is assumed_______________?
comments icon0

A. In thin slabs, 12 mm minimum or diameter of the bar whichever is more

B. For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more

C. At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar

D. All the above
29. The area of the cross-section of a road fully in banking shown in the given figure, is________________?
comments icon0

A. [sb + r (2bd + sd)]/(r s5)

B. [sb + r (2bd + sd)]/(r s)

C. [sb + r (2bd + sd)]/(r s)

D. None of these

32. The measurement is made in square metre in case of_________________?
comments icon0

A. Hollow concrete block wall

B. R.C.C. structure

C. None of these

D. Cement concrete in foundation

33. The plinth area of a building not includes_________________?
comments icon0

A. Area of the walls at the floor level

B. Lift and wall including landing

C. Internal shaft for sanitary installations up to 2 sq m. in area

D. Area of cantilevered porch
34. The rate of payment is made for 100 cu m (per % cu m) in case of__________________?
comments icon0

A. Earth work in excavation

B. All the above

C. Excavation in trenches for foundation

D. Rock cutting

35. Carpet area does not include the area of_________________?
comments icon0
A. All the above

B. Bath room and lavatory

C. The walls along with doors and other openings

D. Kitchen and pantry

36. The item of the brick structure measured in sq.m, is___________________?
comments icon0

A. Brick edging

B. Reinforced brick work

C. Broken glass coping

D. Brick work in arches

37. The assumption on which the trapezoidal formula for volumes is based, is________________?
comments icon0

A. The mid-area of a pyramid is half the average area of the ends

B. The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied

C. The end sections are parallel planes

D. All the above
39. The cross -sections for a highway is taken at_________________?
comments icon0

A. Right angle to the centre line

B. All the above

C. 30 metres apart

D. Intermediate points having abrupt change in gradient

41. In the mid-section formula__________________?
comments icon0

A. The mean depth is the average of depths of two consecutive sections

B. The area of mid-sections is calculated by using mean depth

C. All of the above

D. The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections

43. For the construction of buildings, the subheads of the estimate are________________?
comments icon0

A. Brickwork Flooring, Wood work, Steel work

B. Brickwork, Stone work, Roofing

C. All the above

D. Earthwork, Concrete work, Brick work

45. Anti-siphonage pipe is connected to__________________?
comments icon0

A. Side of water closet

B. Top of P trap W.C.

C. Bottom of P trap W.C.

D. Main soil pipe

47. The brick work is not measured in cu m in case of_______________?
comments icon0

A. Reinforced brick work

B. Half brick wall

C. One or more than one brick wall

D. Brick work in arches

49. Pick up the correct statement from the following?
comments icon0

A. The earthwork calculation in excavation is made from the difference in levels obtained with a level

B. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers

C. In order to check up the average depth of excavation, Dead man s are left at the mid-widths of borrow pits

D. All the above
50. The correct Prismoidal formula for volume is________________?
comments icon0
A. D/3 [first area + last area + 4 Even area + 2 odd areas]

B. D/3 [first area + last area + 2 Even area + 4 odd areas]

C. D [first area + last area + Even area + 2 odd areas]

D. D/6 [first area + odd areas]