construction planning and management Mcqs
1. The reduction in project time normally results in_______________?
comments icon0

A. increasing the direct cost and indirect cost both

B. decreasing the direct cost and indirect cost both

C. increasing the direct cost and decreasing the indirect cost

D. decreasing the direct cost and increasing indirect cost

3. In resources levelling________________?
comments icon0

A. cost of project is controlled

B. total duration of project is increased

C. total duration of project is reduced

D. uniform demand of resources is achieved
4. Grader is used mainly for___________________?
comments icon0
A. finishing, shaping and trimming

B. shaping and trimming

C. finishing and shaping

D. trimming and finishing

6. The area under the Beta distribution curve is divided into two equal parts by_______________?
comments icon0

A. most likely time

B. optimistic time

C. expected time

D. pessimistic time

9. Sensitivity analysis is a study of__________________?
comments icon0

A. comparison of assets and liabilities

B. change in output due to change in input

C. economics of cost and benefits of the project

D. comparison of profit and loss

13. Updating may result in_________________?
comments icon0

A. change of critical path

B. increase of project completion time

C. decrease of project completion time

D. all of the above
17. Latest start of an activity is always________________?
comments icon0

A. less than or equal to latest event time of preceding node

B. greater than or equal to latest event time of preceding node

C. less than latest event time of preceding node

D. equal to latest event time of preceding node

20. The time corresponding to minimum total project cost is_______________?
comments icon0

A. crash time

B. optimistic time

C. between normal time and crash time

D. normal time

21. Which of the following is a weakness of bar chart ?
comments icon0
A. all of the above

B. project progress

C. interdependencies of activities

D. uncertainties

23. Preliminary project report for a road project must contain___________________?
comments icon0

A. the several alternatives of the project that have been considered

B. the contract documents for inviting tenders

C. the detailed estimated cost based on detailed design

D. the soil survey, traffic survey, concept design and approximate cost
27. Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
comments icon0
A. for all activities required to start the work at site on finalization of the contract document

B. for the payment of advances to labour and other staff

C. on commencement of work at site for payment of loan taken by him

D. for the purchase of construction materials

29. Consider the following statements for a power shovel?
comments icon0

A. ect the correct statements?

B. i) Output can be increased by keeping the depth of cut less than optimum depth

C. ) For a given angle of swing, output will be maximum at optimum depth of cut

D. Output can be increased by reducing the angle of swing for a given depth of cut

E. ) Output can be increased by increasing the size of shovel</strong>

31. Which of the following does not represent an activity?
comments icon0
A. site located

B. foundation is being dug

C. the invitations are being sent

D. the office area is being cleaned

32. The process of incorporating changes and rescheduling or replanning is called_______________?
comments icon0
A. updating

B. resource levelling

C. resource smoothening

D. critical path scheduling

34. Interfering float is the difference between__________________?
comments icon0
A. total float and free float

B. total float and independent float

C. free float and independent float

D. none of the above

37. At a work site, statistical quality control of concrete means________________?
comments icon0

A. reduction in wastage of inspection costs

B. applying the theory of probability to sample testing or inspection

C. measurement of risks to eliminate failures

D. reduction in costs for the removal of defects

40. Whenever an activity has zero total float, then_______________?
comments icon0

A. free float of the activity must be zero but independent float need not be zero

B. independent float must be zero but free float need not be zero

C. free float and independent float both must be zero

D. free float and independent float both need not be zero

41. Rolling resistance of a wheel depends upon_____________?
comments icon0
A. Vehicle load

B. ) Grade

C. ect the correct statements?

D. i) Ground</strong>

43. Sinking fund is_______________?
comments icon0

A. a part of the money kept in reserve for providing additional structures and structural modifications

B. raised to meet maintenance costs

C. the fund for rebuilding a structure when its economic life is over

D. the total sum to be paid to the municipal authorities by the tenants

46. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
comments icon0

A. expected time of activity A is greater than the expected time of activity B

B. expected time of activity B is greater than the expected time of activity A

C. expected time of both activities A and B are same

D. none of the above

49. During the construction period, price variation clause in contracts caters to__________________?
comments icon0

A. increase in rates of only important materials

B. variation in cost in materials element, labour element and petrol-oil-lubricant element

C. rate of inflation

D. variation in total cost of the project on an ad hoc basis