civil engineering MCQs – Page 267

Practise multiple-choice questions from civil engineering for competitive examinations and subject revision. Review each marked answer and report any item that may be outdated or unclear.

civil engineering Mcqs
5322. During the construction period, price variation clause in contracts caters to__________________?
comments icon0

A. increase in rates of only important materials

B. variation in cost in materials element, labour element and petrol-oil-lubricant element

C. rate of inflation

D. variation in total cost of the project on an ad hoc basis

5324. Critical path_____________?
comments icon0
A. is always longest

B. may be shortest

C. is always shortest

D. may be longest

5325. In the bar chart planning____________?
comments icon0

A. sider the following statements?

B. progress of work can be measured

C. interdependence of the operations cannot be portrayed

D. spare time of the activities can be determined

E. schedule cannot be updated</strong>

5326. In time-cost optimization of a project, crashing is done____________?
comments icon0
A. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

B. only on activities lying on the orginal critical path and having flatter cost slopes

C. on all the activities

D. on all the activities lying on the critical path

5327. The most suitable type of equipment for compaction of cohesive soils is_________________?
comments icon0

A. Smooth-wheeled rollers

B. Tampers

C. Sheep foot rollers

D. Vibratory rollers

5328. The correct sequence of these activities is________________?
comments icon0

A. sider the following activities in a building construction?

5329. The correct sequence of these operations in tunnel construction is______________?
comments icon0

A. Blasting

B. sider the following operations :

C. Placing steel

D. Drilling

E. Placing concrete</strong>

F. Mucking

5332. Batching refers to________________?
comments icon0

A. weighing accurately, the quantity of each material for a job before mixing

B. adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

C. controlling the total quantity at each batch

D. controlling the quantity of each material into each batch
5333. In the critical path method of construction planning, Free Float can be_____________?
comments icon0

A. greater than Independent Float

B. sider the following statements ?

C. greater than Total Float.

D. equal to Total Float.

E. less than Independent Float. Of these statements</strong>

5334. Which of the following is not a PERT event ?
comments icon0
A. class is being attended

B. bus starts from Jaipur

C. site investigation started

D. sessional work completed

5338. Free float for any activity is defined as the difference between__________________?
comments icon0

A. its earliest finish time and latest start time for its successor activity

B. its earliest finish time and earliest start time for its successor activity

C. its latest finish time and earliest start time for its successor activity

D. its latest start time and earliest start time

5339. PERT technique of network analysis is mainly useful for__________________?
comments icon0
A. research and development projects

B. small projects

C. deterministic activities

D. large and complex projects

5340. Total float for any activity is defined as the difference between________________?
comments icon0

A. its latest finish time and earliest start time for its successor activity

B. its latest start time and earliest start time

C. its latest start time and earliest finish time

D. its earliest finish time and earliest start time for its successor activity