5302. Consider the following statements for a power shovel?
comments icon0

A. ect the correct statements?

B. i) Output can be increased by keeping the depth of cut less than optimum depth

C. ) For a given angle of swing, output will be maximum at optimum depth of cut

D. Output can be increased by reducing the angle of swing for a given depth of cut

E. ) Output can be increased by increasing the size of shovel</strong>

5304. Which of the following does not represent an activity?
comments icon0
A. site located

B. foundation is being dug

C. the invitations are being sent

D. the office area is being cleaned

5305. The process of incorporating changes and rescheduling or replanning is called_______________?
comments icon0
A. updating

B. resource levelling

C. resource smoothening

D. critical path scheduling

5307. Interfering float is the difference between__________________?
comments icon0
A. total float and free float

B. total float and independent float

C. free float and independent float

D. none of the above

5310. At a work site, statistical quality control of concrete means________________?
comments icon0

A. reduction in wastage of inspection costs

B. applying the theory of probability to sample testing or inspection

C. measurement of risks to eliminate failures

D. reduction in costs for the removal of defects

5313. Whenever an activity has zero total float, then_______________?
comments icon0

A. free float of the activity must be zero but independent float need not be zero

B. independent float must be zero but free float need not be zero

C. free float and independent float both must be zero

D. free float and independent float both need not be zero

5314. Rolling resistance of a wheel depends upon_____________?
comments icon0
A. Vehicle load

B. ) Grade

C. ect the correct statements?

D. i) Ground</strong>

5316. Sinking fund is_______________?
comments icon0

A. a part of the money kept in reserve for providing additional structures and structural modifications

B. raised to meet maintenance costs

C. the fund for rebuilding a structure when its economic life is over

D. the total sum to be paid to the municipal authorities by the tenants

5319. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
comments icon0

A. expected time of activity A is greater than the expected time of activity B

B. expected time of activity B is greater than the expected time of activity A

C. expected time of both activities A and B are same

D. none of the above