5351. Crash project duration is obtained by summing the________________?
comments icon0

A. normal durations for all the activities

B. crash durations for all activities

C. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

D. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

5352. For a given size of bucket, the ideal output of a dragline will be least in_______________?
comments icon0

A. Moist loam

B. Wet sticky clay

C. Good common earth

D. Sand and gravel

5353. Earliest finish of an activity is always_______________?
comments icon0

A. greater than or equal to earliest event time of the following node

B. greater than earliest event time of the following node

C. less than earliest event time of the following node

D. less than or equal to earliest event time of the following node
5354. Select the correct statement?
comments icon0

A. The tail of an arrow represents the finish of an activity

B. Activity arrows in a CPM network are drawn to scale

C. none of the above

D. Arrow bead represents the start of an activity

5355. Select the incorrect statement?
comments icon0

A. Start float and finish float are always equal

B. Total float can be either start float or finish float

C. Start float and finish float need not be equal

D. Start float and finish float are the differences between activity times and not event times

5361. Free float is mainly used to_________________?
comments icon0

A. establish priorities

B. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

C. identify the activities, which can be delayed without affecting the total float of succeeding activity

D. identify the activities which can be delayed without affecting the total float of preceding activity

5362. Select the incorrect statement?
comments icon0

A. A critical path always terminates at the last event

B. A critical path always begins at the very first event

C. Critical activities control the project duration

D. Critical activity is the one for which free float is zero
5363. Pick up the excavation where measurements are made in square metres for payment ?
comments icon0

A. Ordinary cuttings up to 1 m

B. Surface dressing up to 15 cm depths

C. Surface excavation up to 30 cm depths

D. Both B. and C.
5364. The inspection pit or chamber is a manhole provided in a base drainage system________________?
comments icon0

A. At every change of direction

B. All the above

C. At every change of gradient

D. At every 30 m intervals

5367. The main factor to be considered while preparing a detailed estimate, is________________?
comments icon0

A. Availability of materials

B. All the above

C. Quantity of the materials

D. Transportation of materials

5368. While preparing a detailed estimate__________________?
comments icon0
A. All the above

B. Dimension should be measured correct to 0.01 m

C. Volume should be measured correct to 0.01 cum

D. Area should be measured correct to 0.01 sqm

5370. The measurement is not made in square metres in case of________________?
comments icon0
A. R.C. Chhajja

B. D.P.C. (Damp proof course)

C. Concrete Jeffries

D. Form works

5371. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken________________?
comments icon0

A. 1.20 litres for 15 users

B. 1.80 litres for 5 to 10 users

C. All the above

D. 1.35 for 20 users

5373. In case of laying gullies, siphons, intercepting traps, the cost includes_______________?
comments icon0

A. Setting and laying

B. Connection to drains

C. All of these

D. Bed concreting

5376. According to ISI method of measurement, the order of the sequence is_________________?
comments icon0

A. None of these

B. Height, length, breadth

C. Length, breadth, height

D. Breadth, length, height

5377. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________?
comments icon0

A. One fourth breadth of wall on each side

B. Breadth of the wall

C. Half breadth of wall on each side

D. None of these

5380. Pick up the correct statement regarding the centre line method of estimating a building?
comments icon0
A. All the above

B. The centre line is worked out separately for different sections of walls of a building

C. The centre line length is reduced by half the layer of main wall joining the partition wall

D. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

5381. The most reliable estimate is_________________?
comments icon0

A. Cube rate estimate

B. Preliminary estimate

C. Plinth area estimate

D. Detailed estimate
5383. The following item of earth work is not measured separately ?
comments icon0

A. Steps in deep excavation

B. All the above

C. Setting out of works

D. Site clearance

5384. The rate of an item of work depends on_________________?
comments icon0
A. All the above

B. Specifications of materials

C. Specifications of works

D. Proportion of mortar

5385. The centre line method is specially adopted for estimating_________________?
comments icon0

A. Circular buildings

B. All the above

C. Hexagonal buildings

D. Octagonal buildings

5386. The measurement is made for stone work in square metre in case of________________?
comments icon0

A. Building work

B. Columns, lintels, copings

C. A. and D. of the above

D. Wall facing

5387. While estimating the qualities for the construction of a building, the correct metric unit is________________?
comments icon0

A. Cubic metre for area

B. Metre for length

C. Square metres for volume

D. Litre for capacity
5388. According to Indian Standards Institute, the actual size of modular bricks is_______________?
comments icon0

A. 25 cm 13 cm 7.5 cm

B. 19 cm 9 cm 9 cmD. 20 cm 10 cm 10 cm

C. 23 cm 11.5 cm 7.5 cm

5390. While estimating a reinforced cement structure, the omitted cover of concrete is assumed_______________?
comments icon0

A. In thin slabs, 12 mm minimum or diameter of the bar whichever is more

B. For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more

C. At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar

D. All the above
5391. The area of the cross-section of a road fully in banking shown in the given figure, is________________?
comments icon0

A. [sb + r (2bd + sd)]/(r s5)

B. [sb + r (2bd + sd)]/(r s)

C. [sb + r (2bd + sd)]/(r s)

D. None of these

5394. The measurement is made in square metre in case of_________________?
comments icon0

A. Hollow concrete block wall

B. R.C.C. structure

C. None of these

D. Cement concrete in foundation

5395. The plinth area of a building not includes_________________?
comments icon0

A. Area of the walls at the floor level

B. Lift and wall including landing

C. Internal shaft for sanitary installations up to 2 sq m. in area

D. Area of cantilevered porch
5396. The rate of payment is made for 100 cu m (per % cu m) in case of__________________?
comments icon0

A. Earth work in excavation

B. All the above

C. Excavation in trenches for foundation

D. Rock cutting

5397. Carpet area does not include the area of_________________?
comments icon0
A. All the above

B. Bath room and lavatory

C. The walls along with doors and other openings

D. Kitchen and pantry

5398. The item of the brick structure measured in sq.m, is___________________?
comments icon0

A. Brick edging

B. Reinforced brick work

C. Broken glass coping

D. Brick work in arches

5399. The assumption on which the trapezoidal formula for volumes is based, is________________?
comments icon0

A. The mid-area of a pyramid is half the average area of the ends

B. The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied

C. The end sections are parallel planes

D. All the above