civil engineering Mcqs
5301. Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
comments icon0
A. for all activities required to start the work at site on finalization of the contract document

B. for the payment of advances to labour and other staff

C. on commencement of work at site for payment of loan taken by him

D. for the purchase of construction materials

5303. Consider the following statements for a power shovel?
comments icon0

A. ect the correct statements?

B. i) Output can be increased by keeping the depth of cut less than optimum depth

C. ) For a given angle of swing, output will be maximum at optimum depth of cut

D. Output can be increased by reducing the angle of swing for a given depth of cut

E. ) Output can be increased by increasing the size of shovel</strong>

5305. Which of the following does not represent an activity?
comments icon0
A. site located

B. foundation is being dug

C. the invitations are being sent

D. the office area is being cleaned

5306. The process of incorporating changes and rescheduling or replanning is called_______________?
comments icon0
A. updating

B. resource levelling

C. resource smoothening

D. critical path scheduling

5308. Interfering float is the difference between__________________?
comments icon0
A. total float and free float

B. total float and independent float

C. free float and independent float

D. none of the above

5311. At a work site, statistical quality control of concrete means________________?
comments icon0

A. reduction in wastage of inspection costs

B. applying the theory of probability to sample testing or inspection

C. measurement of risks to eliminate failures

D. reduction in costs for the removal of defects

5314. Whenever an activity has zero total float, then_______________?
comments icon0

A. free float of the activity must be zero but independent float need not be zero

B. independent float must be zero but free float need not be zero

C. free float and independent float both must be zero

D. free float and independent float both need not be zero

5315. Rolling resistance of a wheel depends upon_____________?
comments icon0
A. Vehicle load

B. ) Grade

C. ect the correct statements?

D. i) Ground</strong>

5317. Sinking fund is_______________?
comments icon0

A. a part of the money kept in reserve for providing additional structures and structural modifications

B. raised to meet maintenance costs

C. the fund for rebuilding a structure when its economic life is over

D. the total sum to be paid to the municipal authorities by the tenants

5320. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
comments icon0

A. expected time of activity A is greater than the expected time of activity B

B. expected time of activity B is greater than the expected time of activity A

C. expected time of both activities A and B are same

D. none of the above

5323. During the construction period, price variation clause in contracts caters to__________________?
comments icon0

A. increase in rates of only important materials

B. variation in cost in materials element, labour element and petrol-oil-lubricant element

C. rate of inflation

D. variation in total cost of the project on an ad hoc basis

5325. Critical path_____________?
comments icon0
A. is always longest

B. may be shortest

C. is always shortest

D. may be longest

5326. In the bar chart planning____________?
comments icon0

A. sider the following statements?

B. progress of work can be measured

C. interdependence of the operations cannot be portrayed

D. spare time of the activities can be determined

E. schedule cannot be updated</strong>

5327. In time-cost optimization of a project, crashing is done____________?
comments icon0
A. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

B. only on activities lying on the orginal critical path and having flatter cost slopes

C. on all the activities

D. on all the activities lying on the critical path

5328. The most suitable type of equipment for compaction of cohesive soils is_________________?
comments icon0

A. Smooth-wheeled rollers

B. Tampers

C. Sheep foot rollers

D. Vibratory rollers

5329. The correct sequence of these activities is________________?
comments icon0

A. sider the following activities in a building construction?

5330. The correct sequence of these operations in tunnel construction is______________?
comments icon0

A. Blasting

B. sider the following operations :

C. Placing steel

D. Drilling

E. Placing concrete</strong>

F. Mucking

5333. Batching refers to________________?
comments icon0

A. weighing accurately, the quantity of each material for a job before mixing

B. adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

C. controlling the total quantity at each batch

D. controlling the quantity of each material into each batch
5334. In the critical path method of construction planning, Free Float can be_____________?
comments icon0

A. greater than Independent Float

B. sider the following statements ?

C. greater than Total Float.

D. equal to Total Float.

E. less than Independent Float. Of these statements</strong>

5335. Which of the following is not a PERT event ?
comments icon0
A. class is being attended

B. bus starts from Jaipur

C. site investigation started

D. sessional work completed

5339. Free float for any activity is defined as the difference between__________________?
comments icon0

A. its earliest finish time and latest start time for its successor activity

B. its earliest finish time and earliest start time for its successor activity

C. its latest finish time and earliest start time for its successor activity

D. its latest start time and earliest start time

5340. PERT technique of network analysis is mainly useful for__________________?
comments icon0
A. research and development projects

B. small projects

C. deterministic activities

D. large and complex projects

5341. Total float for any activity is defined as the difference between________________?
comments icon0

A. its latest finish time and earliest start time for its successor activity

B. its latest start time and earliest start time

C. its latest start time and earliest finish time

D. its earliest finish time and earliest start time for its successor activity

5342. Slack time refers to_______________?
comments icon0

A. an activity

B. an event

C. both event and activity

D. none of the above

5343. In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
comments icon0

A. Poissons distribution curve

B. Beta distribution curve

C. none of the above

D. normal distribution curve

5345. Economic saving of time results by crashing_________________?
comments icon0

A. costliest non-critical activity

B. costliest critical activity

C. cheapest non-critical activity

D. cheapest critical activity
5347. Select the incorrect statement?
comments icon0

A. Earliest start of an activity is the early event time of the node it leaves.

B. Latest finish of an activity is the late event time of the node it enters.

C. none of the above

D. Latest start of an activity is its latest finish minus its duration.

5348. The independent float affects only_______________?
comments icon0
A. the particular activity involved

B. preceding activities

C. succeeding activities

D. none of the above

5349. Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased_______________?
comments icon0
A. Both A and R are true and R is the correct explanation of A

B. Both A and R are true but R is not the correct explanation of A

C. A is true but R is false

D. A is false but R is true

5350. The constraints in case of resource smoothening operation would be_______________?
comments icon0

A. resources

B. project duration time

C. both resources and project duration time

D. none of the above