2102. When the axis of load lies in the plane of rivet group, then the rivets are subjected to________________?
comments icon0
A. only shear stresses

B. only tensile stresses

C. both (A) and (B)

D. none of the above

2104. For the construction of buildings, the subheads of the estimate are________________?
comments icon0

A. Brickwork, Stone work, Roofing

B. Earthwork, Concrete work, Brick work

C. Brickwork Flooring, Wood work, Steel work

D. All the above
2106. Referring of given figure, pick up the correct statement from the following?
comments icon0
A. All the above

B. Length of long wall out-to -out is 6.80 m

C. Length of short walls in-to-in is 3.20 m

D. The total length of centre line of four walls is 20 m

2107. The bending stress in a wall or column subjected to effective vertical load need not be considered, if the eccentricity ratio is_________________?
comments icon0

A. less than or equal to 1/12

B. more than 1/24

C. less than or equal to 1/24

D. less than or equal to 1/6

2110. Size, capacity and materials need be specified for__________________?
comments icon0

A. Bib-cocks

B. All the above

C. Stop-cocks

D. Ball valves

2111. A circular column section is generally not used in actual practice because________________?
comments icon0

A. it cannot carry the load safely

B. all of the above

C. it is difficult to connect beams to the round sections

D. it is uneconomical

2112. The inspection pit or chamber is a manhole provided in a base drainage system________________?
comments icon0

A. At every 30 m intervals

B. At every change of direction

C. At every change of gradient

D. All the above
2117. As compared to field rivets, the shop rivets are________________?
comments icon0
A. stronger

B. weaker

C. any of the above

D. equally strong

2118. Pick up the correct statement regarding the centre line method of estimating a building?
comments icon0

A. The centre line is worked out separately for different sections of walls of a building

B. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

C. All the above

D. The centre line length is reduced by half the layer of main wall joining the partition wall

2120. Pick up the incorrect statement from the following?
comments icon0
A. None of these

B. The carpet area of a building along with area of its kitchen, pantry, store, lavatory, bath room and glazed veranda, is called floor area

C. The built up covered area at the floor level of any storey of a building is called plinth area

D. The usable covered area of the rooms of any storey of a building is called carpet area