construction planning and management MCQs – Page 5

Practise focused construction planning and management questions with marked answers for exam preparation and subject revision.

construction planning and management Mcqs
81. Select the incorrect statement?
comments icon0

A. Start float and finish float are always equal

B. Total float can be either start float or finish float

C. Start float and finish float need not be equal

D. Start float and finish float are the differences between activity times and not event times

87. Free float is mainly used to_________________?
comments icon0

A. establish priorities

B. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

C. identify the activities, which can be delayed without affecting the total float of succeeding activity

D. identify the activities which can be delayed without affecting the total float of preceding activity

88. Select the incorrect statement?
comments icon0

A. A critical path always terminates at the last event

B. A critical path always begins at the very first event

C. Critical activities control the project duration

D. Critical activity is the one for which free float is zero