construction planning and management MCQs – Page 2

Practise focused construction planning and management questions with marked answers for exam preparation and subject revision.

construction planning and management Mcqs
21. Which of the following is a weakness of bar chart ?
comments icon0
A. all of the above

B. project progress

C. interdependencies of activities

D. uncertainties

23. Preliminary project report for a road project must contain___________________?
comments icon0

A. the several alternatives of the project that have been considered

B. the contract documents for inviting tenders

C. the detailed estimated cost based on detailed design

D. the soil survey, traffic survey, concept design and approximate cost
27. Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
comments icon0
A. for all activities required to start the work at site on finalization of the contract document

B. for the payment of advances to labour and other staff

C. on commencement of work at site for payment of loan taken by him

D. for the purchase of construction materials

29. Consider the following statements for a power shovel?
comments icon0

A. ect the correct statements?

B. i) Output can be increased by keeping the depth of cut less than optimum depth

C. ) For a given angle of swing, output will be maximum at optimum depth of cut

D. Output can be increased by reducing the angle of swing for a given depth of cut

E. ) Output can be increased by increasing the size of shovel</strong>

31. Which of the following does not represent an activity?
comments icon0
A. site located

B. foundation is being dug

C. the invitations are being sent

D. the office area is being cleaned

32. The process of incorporating changes and rescheduling or replanning is called_______________?
comments icon0
A. updating

B. resource levelling

C. resource smoothening

D. critical path scheduling

34. Interfering float is the difference between__________________?
comments icon0
A. total float and free float

B. total float and independent float

C. free float and independent float

D. none of the above

37. At a work site, statistical quality control of concrete means________________?
comments icon0

A. reduction in wastage of inspection costs

B. applying the theory of probability to sample testing or inspection

C. measurement of risks to eliminate failures

D. reduction in costs for the removal of defects

40. Whenever an activity has zero total float, then_______________?
comments icon0

A. free float of the activity must be zero but independent float need not be zero

B. independent float must be zero but free float need not be zero

C. free float and independent float both must be zero

D. free float and independent float both need not be zero