construction planning and management MCQs – Page 3

Practise focused construction planning and management questions with marked answers for exam preparation and subject revision.

construction planning and management Mcqs
41. Rolling resistance of a wheel depends upon_____________?
comments icon0
A. Vehicle load

B. ) Grade

C. ect the correct statements?

D. i) Ground</strong>

43. Sinking fund is_______________?
comments icon0

A. a part of the money kept in reserve for providing additional structures and structural modifications

B. raised to meet maintenance costs

C. the fund for rebuilding a structure when its economic life is over

D. the total sum to be paid to the municipal authorities by the tenants

46. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
comments icon0

A. expected time of activity A is greater than the expected time of activity B

B. expected time of activity B is greater than the expected time of activity A

C. expected time of both activities A and B are same

D. none of the above

49. During the construction period, price variation clause in contracts caters to__________________?
comments icon0

A. increase in rates of only important materials

B. variation in cost in materials element, labour element and petrol-oil-lubricant element

C. rate of inflation

D. variation in total cost of the project on an ad hoc basis

51. Critical path_____________?
comments icon0
A. is always longest

B. may be shortest

C. is always shortest

D. may be longest

52. In the bar chart planning____________?
comments icon0

A. sider the following statements?

B. progress of work can be measured

C. interdependence of the operations cannot be portrayed

D. spare time of the activities can be determined

E. schedule cannot be updated</strong>

53. In time-cost optimization of a project, crashing is done____________?
comments icon0
A. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

B. only on activities lying on the orginal critical path and having flatter cost slopes

C. on all the activities

D. on all the activities lying on the critical path

54. The most suitable type of equipment for compaction of cohesive soils is_________________?
comments icon0

A. Smooth-wheeled rollers

B. Tampers

C. Sheep foot rollers

D. Vibratory rollers

55. The correct sequence of these activities is________________?
comments icon0

A. sider the following activities in a building construction?

56. The correct sequence of these operations in tunnel construction is______________?
comments icon0

A. Blasting

B. sider the following operations :

C. Placing steel

D. Drilling

E. Placing concrete</strong>

F. Mucking

59. Batching refers to________________?
comments icon0

A. weighing accurately, the quantity of each material for a job before mixing

B. adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

C. controlling the total quantity at each batch

D. controlling the quantity of each material into each batch
60. In the critical path method of construction planning, Free Float can be_____________?
comments icon0

A. greater than Independent Float

B. sider the following statements ?

C. greater than Total Float.

D. equal to Total Float.

E. less than Independent Float. Of these statements</strong>