1841. Fish plate is in contact with rail at________________?
comments icon0

A. head of rail

B. web of rail

C. fishing plane

D. foot of rail

1843. In the bar chart planning____________?
comments icon0

A. progress of work can be measured

B. interdependence of the operations cannot be portrayed

C. schedule cannot be updated</strong>

D. spare time of the activities can be determined

E. sider the following statements?

1849. Which of the following are percussion drills ?
comments icon0

A. ect correct answer?

B. shot drill

C. ) diamond drill

D. ) churn drill </strong>

E. i) wagon drill

1850. Study the following statements?
comments icon0
A. ="color: #003f1a;">1. Levees are constructed parallel to river flow

B. Spurs are constructed transverse to river flow</strong></span>

C. correct answer is

D. Levees are constructed transverse to river flow

E. Spurs are constructed parallel to river flow

1851. Creep is the_______________?
comments icon0

A. difference in level of two rails

B. vertical movement of rail

C. longitudinal movement of rail

D. lateral movement of rail

1852. Free float for any activity is defined as the difference between__________________?
comments icon0

A. its earliest finish time and latest start time for its successor activity

B. its latest start time and earliest start time

C. its latest finish time and earliest start time for its successor activity

D. its earliest finish time and earliest start time for its successor activity
1854. The process of incorporating changes and rescheduling or replanning is called_______________?
comments icon0

A. resource levelling

B. resource smoothening

C. updating

D. critical path scheduling

1855. Which one of the following is considered to be an advantage of the heading and benching method of tunnel construction?
comments icon0

A. In this method, it is easy to install timber support

B. It is suitable for construction in unstable rocks

C. Tunnelling can be continuous and the work can be expedited

D. In case of excessive water, it is easy to take correct steps

1857. Sensitivity analysis is a study of__________________?
comments icon0

A. comparison of assets and liabilities

B. economics of cost and benefits of the project

C. comparison of profit and loss

D. change in output due to change in input
1858. A pin-jointed plane frame is unstable if________________?
comments icon0

A. (m + r)>2j

B. m + r = 2j

C. none of the above

D. (m + r)