3481. The needle beam method of tunneling______________?
comments icon0

A. ect the answer?

B. ) is suitable for brick lining

C. ) requires large number of trench jacks</strong>

D. i) is suitable for concrete lining

E. is suitable for soils in which roof can stand for few minutes without support
3483. In Belgium method of tunneling _________________?
comments icon0

A. construction of invert and side walls is completed before roof arch is built

B. construction of side walls is completed before invert and roof arch are built

C. construction of invert is completed before side walls and roof arch are built

D. construction of roof arch is completed before side walls and invert are built
3485. The correct sequence of drilling equipment for increasing size of holes in tunnels is________________?
comments icon0

A. shot drill, churn drill, wagon drill

B. wagon drill, shot drill, churn drill

C. wagon drill, churn drill, shot drill

D. churn drill, wagon drill, shot drill

3486. In full face method of constructing tunnels, the first operation relates to______________?
comments icon0

A. excavation of one drift in the centre

B. excavation being done along the periphery

C. removal of bottom portion

D. removal of top portion

3487. American method of tunneling________________?
comments icon0

A. ect the correct answer?

B. ) requires heavy timbers </strong>

C. is no, suitable for railway or highway tunnels

D. is suitable for large sized tunnels
3490. Which one of the following tunnelling methods is used for laying under ground sewers ?
comments icon0

A. Needle beam method

B. Army method

C. German method

D. Italian method

3491. Drifters can be used to drill_________________?
comments icon0

A. only up holes

B. horizontal or up holes

C. horizoral, down or up holes

D. only down holes

3492. What is the correct sequence of the following events of construction of a shaft in rock ?
comments icon0
A. drilling and blasting

B. mucking</strong>

C. timbering

D. pumping

3493. In compressed air tunneling, the volume of free air provided is______________?
comments icon0

A. 20 m3 per minute per m2 of face area

B. 6 m3 per minute per m2 of face area

C. 6 mJ per second per m2 of face area

D. 6 m3 per hour per m2 of face area

3494. Consider the following statements regarding bands to be provided for strengthening masonry work in masonry buildings constructed in zone III, IV and V?
comments icon0

A. ) Gable band is provided at top of gable masonry below the purlins,

B. i) The bands shall be to full width of the wall and not less than 7.5 cm in depth,

C. ) The bands shall be made of reinforced concrete only. </strong>

D. Lintel band is provided at lintel level on partition walls,
3496. A high lime content in a composite cement-lime mortar results in______________?
comments icon0

A. sider the following statements.

B. weaker mortar.</strong>

C. ect the correct statements.

D. slow hardening.

E. quick setting.

3498. Consider the following statements?
comments icon0

A. ch of these statements are correct?

B. Masonry in rich cement mortar though having good strength with high shrinkage is much liable for surface cracks.

C. Lime mortar possesses poor workability and poor water retentivity and also suffers high shrinkage.

D. Masonry in lime mortar has better resistance against rain penetration and is less liable to crack when compared to masonry in cement mortar.</strong>