3901. In A-B-C control policy, maximum attention is given to__________________?
comments icon0

A. proper quality assurance program-mes

B. those items which consume more money

C. those items which consume money

D. those x items which are in more demand

E. those items which are not readily available

3903. In perpetual inventory control, the material is checked as it reaches its__________________?
comments icon0

A. average value

B. alarming value

C. middle value

D. minimum value

E. maximum value

3904. Slack of various events on the critical path in PERT/CPM chart___________________?
comments icon0

A. decreases continuously

B. unpredictable

C. increases continuously

D. remains constant

E. may increase or decrease depending on various factors

3905. Critical Path Net Work helps an engineer_________________?
comments icon0

A. none of the above

B. all of the above

C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. to divert the resources from non-critical advanced activities to critical activities

E. to concentrate his attention on critical activities

3906. Pessimistic time is___________________?
comments icon0

A. the minimum time in which an activity can possibly be accomplished

B. the maximum time which an activity might require

C. the earliest finish

D. the average time required for a job

E. the most probable time considering all conditions

3907. A dummy activity________________?
comments icon0

A. is artificially introduced

B. none of the above

C. all of the above

D. does not require any time

E. is represented by a dotted line

3908. Queuing theory is associated with __________________?
comments icon0
A. waiting time

B. inspection time

C. inventory

D. sales

E. production time

3909. The standard time for a job is_________________?
comments icon0
A. total work content + delay contingency allowance

B. total work content + basic time

C. total work content

D. total work content + relaxation time

E. base time + relaxation time

3910. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?
comments icon0
A. all of the above

B. none of the above

C. TL-EFT

D. latest finish time earliest finish time (EFT)

E. latest start time earliest start time

3913. A big advantage of PERT over Gantt charts is that in the former case_________________?
comments icon0
A. inter-relationship among activities is clearly shown

B. early start and late finish of an activity are clearly marked

C. activities and events are clearly shown

D. activity times are clear

E. critical path can be easily determined

3914. Routing assists engineers in deciding in advance___________________?
comments icon0

A. the flow of material in the plant

B. the layout of factory facilities

C. the methods of proper utilization of manpower

D. the methods of proper utilization of machines

E. normal route of workers through the plant

3915. A CPM family includes____________________?
comments icon0

A. CPP (Critical Path Plotted)

B. MCE (Minimum Cost Expenditure)

C. all of the above

D. CPA (Critical Path Analysis)

E. CPS (Critical Path Scheduling)

3916. Which one of the following represents a group incentive plan ?
comments icon0

A. Bedaux Plan

B. Lincoln Plan

C. Taylor Plan

D. Rowan Plan

E. Halsey Premium Plan

3918. Pick up the correct statement from the following?
comments icon0

A. critical path method is event oriented

B. none of the above

C. critical.path method is not activity oriented

D. programmer evaluation and review technique is not event oriented

E. programmer evaluation and review technique is event oriented

3919. PMTP (predetermined motion time systems) include___________________?
comments icon0

A. MTM (method time measurement)

B. none of the above

C. WFS (work factor systems)

D. BNTS (basic motion time study)

E. all of the above
3920. The important file in making a PERT is__________________?
comments icon0

A. no activity from any event can be started from preceding event till it is completed

B. length of arrow has nothing to do with time

C. every activity must be completed before end point is reached

D. all of the above

E. an event cant be accomplished until activities leading to it are completed

3921. PERT is___________________?
comments icon0

A. an analytic tool in concept

B. based on three time estimates for activities linking up two events

C. all of the above

D. used for research and development projects

E. limit up of event oriented diagrams

3923. Scheduling gives information about____________________?
comments icon0

A. when work should complete

B. that how idle time can be minimized

C. none of the above

D. when work should start and how much work should be completed during a certain period

E. proper utilisation of machines

3924. Queuing theory is used for____________________?
comments icon0

A. job-shop scheduling

B. none of the above

C. inventory problems

D. all of the above

E. traffic congestion studies

3925. The assumption in PERT is__________________?
comments icon0
A. a project can be subdivided into a set of predictable, independent activities

B. commissioning time can be changed, if activities are behind schedule

C. cost of project will always be more than the estimated cost, if no timely corrections are taken

D. a project will always be behind schedule, if left uncorrected

E. activities are fixed and cant be changed ,

3927. The critical path of a network represents_______________________?
comments icon0
A. the minimum time required for completion of project

B. maximum cost required for completion of project

C. none of the above

D. minimum cost required for completion of project

E. the maximum time required for completion of project

3928. Work study comprises following main techniques_________________?
comments icon0

A. value analysis and work measurement

B. method study and time study

C. time study and work measurement

D. method study and work measurement

E. method study and job evaluation

3929. Bin card is used in__________________?
comments icon0

A. assembly shop

B. stores

C. foundry shop

D. workshop

E. administrative wing

3930. What does symbol V employ in work study________________?
comments icon0
A. permanent storage

B. none of the above

C. inspection

D. delay/ temporary Storage

E. operation

3931. PERT analysis is based on____________________?
comments icon0

A. optimistic time

B. all of the above

C. none of the above

D. most likely time

E. pessimistic time

3932. The time which results in the least possible direct cost of an activity is known as________________?
comments icon0

A. none of the above

B. standard time

C. normal time

D. slow time

E. crash time

3934. The two-bin system is concerned with_________________?
comments icon0

A. forecasting sales

B. despatching and expediting

C. ordering procedure

D. none of the above

E. production planning

3935. Micromotion study is__________________?
comments icon0

A. enlarged view of motion study

B. motion study of small components upto mirco-seconds

C. subdivision of an operation into therbligs and their analysis

D. minute and detailed motion study

E. analysis of one stage of motion study

3936. O on a PERT/CPM chart represents____________________?
comments icon0

A. dummy event

B. dangling event

C. an event to be transferred to other network chart

D. an ordinary event

E. a significant event representing some mile-stone

3937. PERT/CPM, techniques can be used for following applications____________________?
comments icon0

A. research and development

B. maintenance jobs

C. once through project

D. all of the above

E. all non-technical jobs

3938. A milestone chart_______________________?
comments icon0

A. depicts the delay of jobs, if any

B. shows the inter dependences of various jobs

C. none of the above

D. all of the above

E. points outgoing ahead of schedule of jobs, if any

3939. PERT is the__________________?
comments icon0
A. event oriented technique

B. time oriented technique

C. work oriented technique

D. target oriented technique

E. activity oriented technique

3940. Pick up the correct statement from the following?
comments icon0

A. if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed

B. if the float of an activity is negative, delay in its performance is bound to delay the completion of project

C. the float may be positive, zero or negative

D. if the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project

E. all of the above
3941. The allowed time for a job equals standard time plus___________________?
comments icon0

A. process allowance

B. unforeseen allowance

C. interference allowance

D. learning allowance

E. policy allowance
3942. The technique for establishing and maintaining priorities among the various jobs of any project is known as___________________?
comments icon0

A. slotting technique for scheduling

B. critical ratio scheduling

C. short interval scheduling

D. event flow scheduling technique

E. none of the above

3943. Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
comments icon0

A. consumes time, but no resources

B. consumes resources but no time

C. consumes neither time nor resources

D. is a dangling event

E. consumes both resources and time

3944. Which of the following is not wage incentive plan_________________?
comments icon0

A. Halsey plan

B. Taylor plan

C. Emerson plan

D. differential piece rate system

E. Rowan plan

3945. Monte Carlo solutions in queuing theory are extremely useful in queuing problems_________________?
comments icon0

A. none of the above

B. involving multistage queuing

C. all of the above

D. that cant be analysed mathematically

E. to verify mathematical results

3946. Pick up the incorrect statement from the following. A critical ratio scheduling____________________?
comments icon0

A. determines the status of each activity

B. establishes the relative priorities among various activities on a common basis

C. none of the above

D. adjusts automatically changes in activity progress

E. is a dynamic system

3947. Work study is concerned with_________________?
comments icon0
A. improving present method and finding standard time

B. improving production planning and control

C. improving production capability

D. all of the above

E. motivation of workers

3948. String diagram is used_________________?
comments icon0

A. for checking the relative values of various layouts

B. when a group of workers are working at a place

C. none of the above

D. all of the above

E. where processes require the operator to be moved from one place to another

3949. One of the basic essentials of an incentive plan is that_________________?
comments icon0

A. a differential piece rate system should exist

B. minimum wages should be guaranteed

C. provide incentive to group efficiency performance

D. all standards should be based on time studies

E. all standards should be based on optimum standards of production

3950. Bar charts are suitable for_____________________?
comments icon0

A. none of the above

B. large projects

C. all of the above

D. major works

E. minor works