software management MCQs – Page 5

Practise focused software management questions with marked answers for exam preparation and subject revision.

software management Mcqs
81. Which of the following strategies means that the impact of the risk will be reduced ?
comments icon0

A. Contingency plans

B. All of the mentioned

C. Minimization strategies

D. Avoidance strategies

83. Which model assumes that systems are created from reusable components, scripting or database programming ?
comments icon0

A. A post-architecture model

B. A reuse model

C. An application-composition model

D. An early design model

84. What threatens the quality and timeliness of the software to be produced ?
comments icon0
A. Technical risks

B. Known risks

C. Business risks

D. Project risks

85. What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
comments icon0

A. Degree of Rigor

B. Adaptation criteria

C. Task Set

D. Both degree of Rigor and adaptation criteria

88. Which type of software engineering team has a defined leader who coordinates specific tasks and secondary leaders that have responsibility for sub tasks ?
comments icon0
A. Controlled decentralized (CD)

B. Democratic decentralized (DD)

C. None of the mentioned

D. Controlled centralized (CC)

90. Which one is not a size measure for software product ?
comments icon0

A. Halsteads program length

B. Cyclomatic Complexity

C. LOC

D. Function Count

91. Which version of COCOMO states that once requirements have been stabilized, the basic software architecture has been established ?
comments icon0

A. Post-architecture-stage model

B. All of the mentioned

C. Application composition model

D. Early design stage model
92. Which of the following is not a Software Configuration Management Activity ?
comments icon0
A. Risk management

B. Branch management

C. Release management

D. Configuration item identification

94. A sequence of baselines representing different versions of a system is known as ____________________?
comments icon0

A. System building

B. None of the mentioned

C. Mainline

D. Software Configuration Item(SCI)

95. SPMP stands for__________________?
comments icon0
A. Software Project Management Plan

B. Software Project Managers Plan

C. Software Product Managers Plan

D. Software Product Management Plan

97. Which of the following is not a business risk ?
comments icon0

A. losing budgetary or personnel commitment

B. lack of documented requirements or software scope

C. building an excellent product or system that no one really wants

D. losing the support of senior management due to a change in focus or change in people