1. Pick up the excavation where measurements are made in square metres for payment ?
comments icon0

A. Ordinary cuttings up to 1 m

B. Surface dressing up to 15 cm depths

C. Surface excavation up to 30 cm depths

D. Both B. and C.
2. The inspection pit or chamber is a manhole provided in a base drainage system________________?
comments icon0

A. At every change of direction

B. All the above

C. At every change of gradient

D. At every 30 m intervals

5. The main factor to be considered while preparing a detailed estimate, is________________?
comments icon0

A. Availability of materials

B. All the above

C. Quantity of the materials

D. Transportation of materials

6. While preparing a detailed estimate__________________?
comments icon0
A. All the above

B. Dimension should be measured correct to 0.01 m

C. Volume should be measured correct to 0.01 cum

D. Area should be measured correct to 0.01 sqm

8. The measurement is not made in square metres in case of________________?
comments icon0
A. R.C. Chhajja

B. D.P.C. (Damp proof course)

C. Concrete Jeffries

D. Form works

9. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken________________?
comments icon0

A. 1.20 litres for 15 users

B. 1.80 litres for 5 to 10 users

C. All the above

D. 1.35 for 20 users

11. In case of laying gullies, siphons, intercepting traps, the cost includes_______________?
comments icon0

A. Setting and laying

B. Connection to drains

C. All of these

D. Bed concreting

14. According to ISI method of measurement, the order of the sequence is_________________?
comments icon0

A. None of these

B. Height, length, breadth

C. Length, breadth, height

D. Breadth, length, height

15. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________?
comments icon0

A. One fourth breadth of wall on each side

B. Breadth of the wall

C. Half breadth of wall on each side

D. None of these

18. Pick up the correct statement regarding the centre line method of estimating a building?
comments icon0
A. All the above

B. The centre line is worked out separately for different sections of walls of a building

C. The centre line length is reduced by half the layer of main wall joining the partition wall

D. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

19. The most reliable estimate is_________________?
comments icon0

A. Cube rate estimate

B. Preliminary estimate

C. Plinth area estimate